Five hundred feet of very old, 26 inch steel pipe at the head end of LID 04 will be replaced by CID during the off-season. The pipe and head gate replacement has been planned since June and will provide better control of the water delivery without the worry of a huge washout.

The cost of the project will be spread over a two year period thus keeping the cost increases for maintenance to a minimum.